1.1 BDB/the Defendant
had appointed HGT / the Plaintiff as contractor to extract
timber at "Project Pembinaan Trans Eastern Kedah Interland
Highway from Durian Burung to Kupang, Kedah" via two
(2) Letter of Awards ("LA") dated 21st June 2006 (1st LA)
and 19th August 2007 (2nd LA) respectively for logging sub-contract.
1.2 HGT/the Plaintiff is claiming that based on the 1st
LA, the area for logging should have been 714 hectares whereas
they could apparently extract timber from only 185 hectares,
thus resulting in a shortfall of 528.83 hectares.
HGT/the Plaintiff is therefore suing BDB/the Defendant
alleging breach of contract and is claiming RM 22,432,588.50
as damages.
1.3 In its statement of defence, filed by BDB's/ Defendant's
solicitors, Messrs Vazeer, Akbar, Majid & Co on 5th
August 2009, BDB/the Defendant contended that:-
i) HGT/the Plaintiff never suffered any losses by its own
admission in its summons that it made a net profit of more
than RM6.0 million.
ii) It is not BDB's/ the Defendant's responsibility to
ensure that there are logs in the entire 714 hectares.
On the contrary HGT/the Plaintiff like any other logging
contractor should have done its own survey on Timber
availability.
iii) HGT/the Plaintiff had been found guilty by Jabatan
Perhutanan Negeri Kedah (JPNK), which fact is admitted by
HGT/the Plaintiff by paying the compounds imposed, of the
following offences committed during the tenure of the logging
contract:-
a. Illegal logging outside the approved areas, which act
tarnished the image of BDB/the Defendant;
b. Damage to Public roads;
c. Landslide caused by irresponsible logging; and
d. Polluting and clogging up rivers flowing through the
concession area.
iv) HGT/the Plaintiff failed to complete the logging activities
within the stipulated contract time frame resulting in monetary
losses to BDB/the Defendant as at the material point in
time BDB/the Defendant was the contractor for a major road
project in that area, namely the "Trans Eastern Kedah Interland
Highway from Durian Burung to Kupang, Kedah."
v) In the view of the aforementioned breaches on the part
of HGT/ the Plaintiff, BDB/the Defendant in counterclaiming
an amount of RM 30 million against HGT/the Plaintiff representing:-
a. Exemplary damages for RM 30 million;
b. Secret profits made by HGT/the Plaintiff through illegal
logging;
c. Aggravated damages;
d. General damages.
1.4 In addition to the counter claims, BDB/the Defendant,
through its solicitor, had on 7th September 2009 filed an
application for striking off the Writ of Summons filed by
HGT/the Plaintiff under Order 18, Rule 19 of High Court
Rules 1980 on the following grounds:-
a. It has no basis of claim;
b. It is scandalous, frivolous and vexatious;
c. It may prejudice, embarrass or delay the fair trial
of the action;
d. It is an abuse of the process of the Court.
The court has fixed 10th November 2009 as the date to hear
the petition to strike off filed by BDB/the Defendant.
2.0 Withholding of Material Information Pursuant
to Paragraph 9.05 of the Bursa Malaysia Listing Requirements.
BDB delayed this announcement so as not to prejudice
its case as it pursued its objectives to file a striking
off application and counter claims.
3.0 Financial and Operational Impact of the Group
At this moment, the legal action is not expected to have
any adverse material impact on the earning and Net
Tangible Assets of BDB.
4.0 Steps Proposed to be Taken
The Directors have instructed its solicitors to take all
appropriate legal actions to defend the interests, good
standing and innocence of BDB.
5.0 Directors and Substantial Shareholders' Interest
None of the Directors and substantial shareholders of BDB
or person connected to the Directors and substantial shareholders
has any interest, whether direct or indirect in the said
contract.
This announcement is dated 20th October 2009.